As we are developing the web interface at a rapid pace, one of the more advanced features has recently been added: the bill of materials (BOM). From now on, you can also manage the production process through the web interface.
Before we dive into the web interface, we should not forget that production can also be managed through the desktop application. However, when it comes to the bill of materials, the web interface is currently just as "smart" as the desktop application.
Now let's move on to a concrete demonstration in the web interface. As mentioned, from ABRA Flexi's perspective, the bill of materials is certainly an advanced feature. It follows that the best way to learn how to work with a bill of materials and the production process is through a concrete example.
⚠️ The bill of materials is available from the Premium license tier. In lower tiers, you will not find the Bill of materials tab in the price list.
Setting up a bill of materials
The essential foundation for production in Flexi is setting up the bill of materials, i.e. the product structure. A bill of materials can be set up for both a finished product and a semi-finished product used to make the finished product.
The product, the semi-finished products, and the end materials must each be created as a separate item in the price list. We recommend separating the individual items by stock type and goods group.
As goods groups are a user-definable code list, the classification is entirely up to you. For our demonstration, however, we will use a basic classification. So we will create the following items in the price list.
As an example, let's choose a bicycle. It will consist of several end materials and two semi-finished products.
Bicycle
finished product; stock type: Product; Goods group: Goods
Front wheel
semi-finished product; stock type: Semi-finished product; Goods group: Semi-finished product
Rear wheel
semi-finished product; stock type: Semi-finished product; Goods group: Semi-finished product
Handlebars; Hub; Derailleur; Spokes
material; stock type: Material; Goods group: Material
each of the 4 components above must be created as a separate price list item
All of the items above must be created in the price list. Once you have done so, we can move on to setting up the bill of materials for the bicycle.
The exact composition of the bicycle is as follows:
Front wheel 1x (consists of 1x Hub; 1x Rim; 32x Spoke)
Rear wheel 1x (consists of 1x Hub; 1x Rim; 32x Spoke)
Handlebars 1x
Derailleur 1x
The bill of materials can always be set up in the detail of a price list item. So let's go to the price list itself, where we will create the finished product, i.e. the bicycle.
The bill of materials is not displayed by default in the price list item detail. If the Bill of materials tab is not offered in the product detail, you can easily enable it using the form settings.
The bill of materials must be created first. You do this using the "Create bill of materials" button on the "Bill of materials" tab in the price list item detail.
Once the bill of materials has been created, we can add to it (on the right-hand side, after hovering the cursor over the row) the individual materials and semi-finished products that the bicycle consists of.
However, the front and rear wheels are semi-finished products for Flexi, i.e. additional items that contain a bill of materials. So we must create it in the price list item detail as well. The bill of materials for the front and rear wheels will look exactly the same.
Once our bills of materials are set up this way, we can move on to the next essential step.
Recalculating bill of materials prices
We can manually recalculate the price of a product directly in its bill of materials, both the sales price and the purchase price. The purchase price is always based on the purchase prices of the materials (as stated in the price list), and the sales price is, in principle, based in the same way on the sales prices of the materials.
You can find this option under the "More functions" button in the header of the bill of materials.
Warehouse mapping
In connection with the bill of materials, Flexi needs to know which warehouse to deduct the material from (or semi-finished product) required to produce the finished product (that is, the material set up in the bill of materials).
The entire procedure is described in a separate guide. Please refer to it directly and follow the recommended steps.
Once the warehouse mapping is set up, we can move on to the next step.
Product order
Let's say we receive a customer order for a bicycle. We create a received order with the bicycle and want to let production know that a new bicycle needs to be produced.
Production order
Production orders are recorded among issued orders. To separate standard issued orders from production orders, we always recommend creating a separate issued order type.
Once we have created an issued order type, we can create a production order from the received order. So we switch back to the received order and create an issued order from it, i.e. a production order.
You can do this simply by selecting the issued order type.
Order for production
When creating a production order, two scenarios can occur. We either have enough or not enough material in stock. If we have enough material, we can create a goods receipt of the product into the warehouse directly from the production order.
However, if we do not have enough material, it needs to be ordered. This is handled by the "Order for production" function. You can generate it from the production order detail.
After you confirm the order generation, a form will open showing the product broken down into individual materials. If the product contains semi-finished products, these will also be broken down into end materials.
We recommend using an order type that is different from the production order. An order for production is simply a standard order placed with a supplier.
Product receipt
Once we have enough materials and semi-finished products in stock, we can move on to the main step. That is, of course, the product receipt and the associated issue of the consumed material.
A product receipt cannot be created when the material is not in stock. It is not possible to generate an issue request here.
However, before we create the product receipt itself, let's look at how to set up stock document types so that we can create the stock movements mentioned above very easily.
Stock document types
Production always has two sides: the receipt of the product and the issue of the consumed material. We can capture both of these operations using stock document types.
So we will create two stock document types:
PRODUCTION-RECEIPT; Product receipt
PRODUCTION-ISSUE; Issue of consumed material
First, we will create the issue of consumed material. Apart from the accounting settings, the only key setting here is "Movement type".
We do not define the warehouse here. The warehouse from which the material is to be issued is determined by the warehouse mapping mentioned earlier.
Next, we will create the product receipt. There are more settings here, apart from accounting.
For example, we can predefine the warehouse into which the finished product should be received by default.
We must define the movement type and the movement type specification (the value "Product receipt" is the key piece of information for Flexi, upon which it starts searching the bill of materials).
To simplify and partially automate the process, it is useful to fill in "Production document type", where we enter the previously created type "PRODUCTION-ISSUE". This determines which stock document type will be used to issue the consumed material.
Once we have created the stock document types, we can return to the product receipt itself.
A product receipt can be created independently as well as by fulfilling a production order. If you do not need a production order, simply go to the goods receipts/issues agenda and create the product receipt there on its own. In our case, however, we will stick to the example for the finished product and create the receipt from the production order.
Producing semi-finished products
Since our product contains semi-finished products, they must be produced first. Flexi cannot perform "intermediate production" of semi-finished products. It always needs exactly the item that is in the bill of materials to be in stock.
So among goods receipts/issues, we create a new receipt with the stock document type "PRODUCTION-RECEIPT" and add the front and rear wheels to it.
When you save the receipt, an issue document for the consumed material is created automatically.
At the same time, the price of the semi-finished products is calculated from the consumed material. You can find the price when you switch back to the product receipt.
Product receipt
We have the semi-finished products in stock, so only the last key step remains. You guessed it: it is nothing other than the receipt of the finished product, which for us is the bicycle.
So we switch back to the production order among the issued orders and create a receipt from it using the services at the bottom.
As the document type, we select product receipt, and as the warehouse, we select the product warehouse (that is, the one into which we want to receive the bicycle). We then confirm the creation of the receipt with the "Create" button.
We are informed about the creation of the product receipt and the issue document for the consumed material by a notification in the bottom left corner.
Here again, based on the earlier stock document type settings, the issue document was created automatically. At the same time, the cost price of the bicycle was automatically calculated from the consumed material.
Now comes the cherry on top: selling the product we have just made. We can switch back to the received order and create an invoice from it together with an issue document.
In connection with production, you can have a wide range of custom outputs created, known as user queries. Are you missing an overview of work in progress in Flexi, or of how much material is missing from stock? Or do you need to analyze the production costs of individual products in detail? User queries can solve both of these needs and much more.
Product receipt reports insufficient material
This error means that when receiving a product, Flexi tries to issue material from stock according to the bill of materials, but there is not enough of it in the relevant warehouse. Proceed as follows:
Identify the warehouse from the error message. The message states which warehouse the material is being issued from and how much is missing.
Check the warehouse mapping. The material warehouse is determined by the warehouse mapping based on the price list item, goods group, and cost center. If the receipt has a different cost center than you expect, a different mapping is used, and therefore a different warehouse.
Verify the material stock level in the specified warehouse. The material must be in stock as of the date of the product receipt.
Check the receipt document type. It must have the movement type specification Product receipt and a reference to the production document type. A type intended for a transfer document cannot be used for a product receipt.
ℹ️ The material warehouse may differ from the warehouse into which the product is received. The product warehouse is determined by the receipt, while the material warehouse is determined by the warehouse mapping.
Do not hesitate to contact us if needed.
Technical support: +420 371 124 321, podporaflexi@abra.eu